Permits on a House Flip: What Needs One, What Is Exempt, and the Cost of Skipping It

Before the next kitchen, bathroom, electrical or roof task continues, write down the exact work and ask the local permit office about that scope. This checklist gives you a first screen. It does not replace the city or county rule that applies to the house.

Start with the adopted local code

The 2024 International Residential Code (IRC), section R105.1, is a model-code starting point, not an automatic rule for every U.S. house. It says an owner or authorized agent must first apply for and obtain a permit for covered construction, enlargement, alteration, repair, moving, demolition, occupancy changes, and regulated electrical, gas, mechanical or plumbing-system work. The local jurisdiction decides which code edition and amendments apply.

The same 2024 IRC section R105.2 lists work exempt from a permit, including painting, papering, tiling, carpeting, cabinets, countertops and similar finish work. It also says an exemption does not authorize work that violates the code or another applicable law or ordinance. That is why the label "like-for-like" is not enough: fixed wiring, piping, layout, structure and local amendments can change the answer.

A building permit, a contractor license or registration, and a specialty-trade credential are separate checks. Use the contractor-license guide alongside the local permit office's answer.

House-flip permit checklist

Examples from Rochester, NY and Portland, OR - verify your local rule before work. This is a comparison, not a nationwide permit chart. The cited city pages were checked October 20, 2026.

Kitchen

Bathroom

Electrical

Roof

For the kitchen, bathroom and roof entries, see the Rochester building-permit guidance and Portland's residential permit checklist, checked October 20, 2026. For Portland's hard-wired electrical rule, see its residential electrical-permit page, checked October 20, 2026. Both cities show why a cosmetic description cannot settle a permit question.

If you have already started

Do not assume an after-the-fact permit has one national result. In Portland, City Code 24.10.060 allows a stop-work order requiring work to stop immediately and completely; written City approval is needed to restart. Portland's electrical enforcement rule allows investigation, correction requirements, civil penalties under applicable law, and an investigation fee for the City's added compliance-check cost. Rochester says required work cannot move to the next stage without required inspection and approval, and that late permits or missed inspections can cause delays or penalties.

Baltimore gives a more serious local example. Under Baltimore Building Code section 114, a person doing work without a required permit must stop, obtain the permit, and pay fees or penalties. The Building Official can require restoration unless compliant work is allowed to remain. The same section provides for a criminal fine of up to $500 per offense and, in a specified equity proceeding, a civil fine of up to $500 per day for unabated violations. Those are Baltimore rules, checked October 20, 2026, not a nationwide price list.

Example only, not a real property or a national fee benchmark: If a Miami permit's scheduled fee is $X, the City of Miami fee schedule, adopted April 23, 2026, says Homestead work begun before a required permit is 2 x $X + a $110 base fee. Its "all other properties (Commercial)" schedule is 4 x $X + a $110 base fee. Confirm the property's classification and the current schedule with Miami before using either multiplier.

Resale and insurance: document the answer you get

Unpermitted work can remain a resale issue even after the job is physically complete. California's 2026 Real Estate Law excerpts show that the statutory Real Estate Transfer Disclosure Statement asks covered residential sellers whether they know of alterations, repairs or modifications made without necessary permits and whether work did not comply with building codes. For a covered single-family-home offer accepted within 18 months after the seller took title, the same excerpts describe a separate contractor-improvement disclosure rule. When the seller contracted with a third party for covered improvements and was not provided copies of permits obtained, the seller may instead provide written notice and the third party's contact information. These are California disclosure examples, not a universal bar to sale.

In Baltimore, section 114 requires a transferee to obtain a violation report before transfer. When violation or condemnation notices are included, the transferee becomes primarily liable to abate them. Keep permits, approved plans, inspection records, invoices and contractor details with the deal file.

The cited sources do not establish an automatic insurance denial for unpermitted work. Coverage can be policy- and claim-specific, so ask the insurer how the actual scope and documentation affect the policy rather than promising a coverage outcome.

Five steps before work continues

  1. Pause the affected work and write down the exact scope: finishes, layout, wiring, piping, structure and roof materials.
  2. Check the city or county's adopted-code, building-permit and trade-permit pages. Do not use Rochester or Portland as your local answer.
  3. Ask the permitting authority whether the exact scope needs building, electrical, plumbing or mechanical permits, and whether plans or inspections are required.
  4. Check who may do the work and who must hold each credential. A permit does not replace a contractor or trade-license requirement.
  5. Save the permits, approved plans, inspection approvals, invoices and contractor details for the resale file.

Before you make or revise an offer, add permit, inspection, correction, holding and contractor costs to the written deal budget. Choosing a house-flip offer multiplier shows where those known costs belong in the offer calculation.

This is general information, not legal advice. Permit, inspection, contractor, disclosure and insurance rules vary by state and locality. Confirm the exact scope with the permitting authority before work continues.